PROJECT BRIEF
Project for Construction of Lompoul Fisheries Center

OUTLINE OF THE PROJECT
Lompoul, in Louga Region, Senegal, is located at the center of major fishing areas and has abundant resources, but a lack of fisheries infrastructure made it difficult to maintain hygiene and sell fish at fair prices. In addition, as desertification advanced, more people were turning from farming to fishing. This project constructed landing and handling areas, ice-making and ice storage facilities, salted and dried fish processing areas and storehouses, and a women's meeting hall, aiming to improve the productivity and working conditions of artisanal fisheries. It also provided the newly established management committee and cooperatives with guidance on operations and financial management, and carried out awareness-raising activities for users.

The Client
DIRECTION DES PECHES MARITIMES, MINISTERE DE L'ECONOMIE MARITIME DE LA REPUBLIQUE DU SENEGAL (DPM)
Location
Lompoul, Louga Region
Construction Term
Mar., 2007
The Consultant
Fisheries Engineering Co., Ltd.
The Contractor
TOA CORPORATION
Facilities
<Civil Works>
Facilities
<Architectural Works>
1. Fish landing and distribution area
- Fish Landing shed facilities (Floor area: 588 sq.m.)
- Ice-making facilities (Floor area: 210 sq.m.)
- Parking lot, etc.
2. Fish processing area
- Dry stands
- Rest station for work (Floor area: 250 sq.m.)
- Meeting House for females (Floor area: 84 sq.m.)
- Storage for dried fish (Floor area: 221 sq.m.)
- Toilet, etc.
3. Support facilities for fishermen
- Administration building (Floor area: 346 sq.m.)
- Fishermen’s locker (Floor area: 778 sq.m.)
- Tower of beacon
4. Others
- Well
- Elevated water tank, etc.
Equipment
1. Fish landing and Processing Equipment
- Fish containers, Insulated boxes, Scales for weighing, etc.
2. Audiovisual Equipment for Meeting room
- Video projector, Computers, Screen, etc.
3. Radiotelephone Equipment
- SSB Radiotelephone
- VHF Radiotelephone
Other
Soft components by FEC
- Support the establishment of the Steering Committee, etc.
Survey Period: March 2004 to August 2004