Project for Construction of Lambarene Fisheries Center

Project for Construction of Lambarene Fisheries Center
OUTLINE OF THE PROJECT

The Client

LA DERECTION GENERALE DES PECHES ET DE L'AQUACULTURE REPUBLIQUE GABONAISE (DGP)

Location

Lambarene, Moyen-Ogooue Province, Gabonese Republic

Construction Term

September 2005

The Consultant

Fisheries Engineering Co., Ltd.

The Contractor

TOA CORPORATION

Facilities
<Civil Works>

1. Fish Landing Dock
 - Steel sheet pile structure
 - Length:85m x 30 m
2. Pontoon Jetty
 - L 30 m x W 4 m x 2 units

Facilities
<Architectural Works>

1. Fisheries Center Building (Floor area: 532 sq.m.)
 - Ice-making machine (Capacity: 6ton/day)
 - Ice Storage (Capacity: 12ton)
 - Fish handling area
 - Fishermen’s locker
 - Staff room
 - Cashier's room, etc.
2. Workshop (Floor area: 33 sq.m.)
 - Workshop for Outboard engine
 - Storage
3. Administration building (Floor area: 325 sq.m.)
 - Administrative office
 - Meeting room
4. Others
 - Public toilet
 - Guard's post
 - Parking lot

Equipment

1. Fish landing equipment
 - Fish containers, Pull cars, Platform scales, etc.
2. Workshop Equipment
3. Computers