PROJECT BRIEF
Project for Construction of Fish Market Center at Majuro Atoll

OUTLINE OF THE PROJECT
In the Marshall Islands, population concentration in the capital, Majuro, and the economic gap with the outer islands were serious issues. Transporting fish from the outer islands to the capital for sale was important both for outer island fishers' incomes and for the capital's food supply. However, there were only two aging vessels capable of ocean voyages, and sales facilities were inadequate, so the supply of fresh fish to the capital was limited. This project constructed a landing wharf and a fish market and provided fish collection and transport vessels, aiming to expand income opportunities for outer island fishers and to ensure a stable supply of fresh fish to the capital. It also provided training in fresh fish handling.

The Client
Marine Resources Authority, Republic of the Marshall Islands (MIMRA)
Location
Uliga Dock, Majuro
Construction Term
Jan., 2011
The Consultant
Fisheries Engineering Co., Ltd.
The Contractor
DAI NIPPON CONSTRUCTION
Facilities
<Civil Works>
1. Dock
- Steel sheet pile structure
- Length:90m (berth length:40m)
2. Land reclamation
- Volume: about 7,400 cu.m.
3. Apron paving
- Concrete paving: 600 sq.m.
4. Ancillary facilities
- Derrick crane, Bit, Fender, Curb
Facilities
<Architectural Works>
1. Fish market center building (Floor area: 406.0 sq.m)
- Ice-making machine (Capacity: 1ton/day)
- Ice Storage (Capacity: 2ton)
- Chilled storage (Capacity: 0.5ton)
2. Water catchment tank (Capacity: 20 cu.m.)
3. Elevated water tank (H=10.8m)
4. Other facilities
- Toilet, Garbage depository, Solar power system, Parking lot
5. Equipment for the market
- Fish carrying boxes, Carts, Insulated tanks, Fish storage boxes, Band saw, SSB radiotelephones, VHF radiotelephones, etc.
Equipment
Fish collection boats
- 2 boats
- Hull material: FRP (Fiberglass Reinforced Plastic)
- Length overall: 16.0 m
- Breadth: 3.2 m
- Gross tonnage: 14 ton (International)
- Fish hold capacity: about 5 cu.m. (Divided into 6 compartments)
The Supplier for Boats
- NBK Corporation
Construction Term
- November 2009 to August 2010
Other
Soft components by FEC
- Improvement of fish quality
- Improvement of fish handling
- Improvement of fish processing, marketing and hygiene
- Improvement of public relations
Survey Period: July 2008 to February 2009





